Productivity Chart
| BUDGET: | HOURS | 495 QUARTER PROJECT | ||||||||||
| TEAM | ||||||||||||
| 1.NAME: Joe Young | 2.NAME: Devin Cottier | 3.NAME: Mark Connaughton | 4.NAME: Rob Lancaster | |||||||||
| WEEK | 1-tasks | 1-hrs | 2-tasks | 2-hrs | 3-tasks | 3-hrs | 4-tasks | 4-hrs | PROJ % DONE | HOURS: BUDGET & USED | COMMENTS | OK's PRF/CST |
|
end 10/14 |
Joe wrote the event class for this weeks mini project | 9 | Devin worte the priority queue class for this weeks mini project | 9 | Mark Wrote the Gui for this weeks mini project | 9 | Rob wrote the simulation class for this weeks mini project | 9 | 100% | 36 Hours |
The team worked well together to complete the project for this week and finish documentation on the requirments |
|
| end 10/21 | Joe completed Functional Requirements and design of Our base events. Wrote the quality plan for the specifications document. | 10 | Devin Cleaned up last weeks java code. Made a prototype map for project and completed the functional design of base vehicle class | 10 | Mark Designed the base coodinate system for the project. Had to miss Sunday meeting, was at home. Also wrote overview and performace requirements for specification document | 10 | Wrote the functional design for the Simulation class. Wrote the remaining parts of the specification document. | 10 | 5% | 40 | The main tasks were to udate java project and finish the specifications document to do this we needed to compleate some design. | |
| end 10/28 | Joe wrote system tests for his use cases and did some simulation coding wrote CRC card for his classes | 10 | Devin did GUI coding for the simulation and also did some work on the dialog class and finished the ER model. Wrote CRC cards for his classes | 10 | Mark did some work on cleaning up the wiki and some restructuring of the project. Wrote CRC cards for his classes | 10 | Rob wrote the system tests that were not done by joe and made changes to the process document. Wrote CRC cards for his classes | 10 | 5% | 40 | The main tasks for this week were to get documentation edited and do CRC cards and ER diagram for project. | |
| end 11/04 | Joe worked with Devin on Sequence Diagrams proof all Documents | 10 | Devin worked with Joe on Sequence Diagrams, prof read all documents | 10 | Made CRC Cards and updated wiki | 10 | Updated Documentation and specifications brough gannt chart and tracking document up to date | 10 | 9% | 40 | Need to finish all documentation and design | |
| end 11/11 | Joe worked on finishing up class design on the vehicle class. Also work on sequence diagrams | 10 | Devin worked on GUI Design and finishing up sequence diagrams. Also added implementation to the gannt chart | 10 | Mark Finished up the CRC cards for the classes | 10 | Rob Worked on finishing up documentation and and design on the simulation class | 10 | 40 | Finish Design | ||
| end 11/18 | ||||||||||||
| end 11/25 | ||||||||||||
| end 12/02 | ||||||||||||
| end 12/09 | ||||||||||||
Show Wiki activity